Last Updated: October 11, 2023By Categories:

SAN DIEGO DESIGN-BUILD SERVICES

  • Total Value of Contract: $3.7M | (Program $3B)
  • Contract Duration: 14 Years (Ongoing)
  • Client: San Diego County Regional Airport Authority
For this $3B program, RIB U.S.COST provided Professional Estimating Services to the Airport Authority from the inception of the Airport Masterplan (AMP2) in the early 2000’s to the present construction of the $690M Terminal 2 West Expansion Program which is a 3-story, 10 gate expansion with a LEED Silver Certification from the United States Green Building Council.

SERVICES PROVIDED:

  • Program Level Budget Estimates, scheduling, phasing and logistics support services during the preconstruction period to validate the various deliverables provided by the Design-Build Team
  • In depth schedule analysis of resource requirements by activity for both landside and terminal contractors
  • Met with each contractor team and each project management team where we developed schedule improvements based on the initial analysis
  • Assisted airport group in reaching a Guaranteed Maximum Price (GMP) with the CM at Risk, Independent Estimates for all scope remaining to be bid out
  • Reconciliation with the CM at Risk on a line by line basis in order to reach a fair value
  • Review and assessment of CM proposed contingencies and fees to assist the SDCRAA in reaching a GMP

RESULTS OF THE PROJECT/CONTRACT

Recognition by the Aviation Director

ACCOMPLISHMENT

Successful Negotiation of GMP contracts for the T2 GreenBuild Project and parking plaza

WORK PERFORMED

Planning & Design Level Estimating Services (Cost Estimating), Cost Validation, Scheduling, Dispute Resolution (Negotiations for CM at Risk Contract) Change Order Management / Review